I manually changed the overall % Complete and now it won't auto calculate

Collen Geter
✭✭
Because I hadn't filled in all my dates, I was asked for a number to represent where I thought we were. So I manually typed in over the % complete auto calculated field and now I can't get it to auto calculate the overall % complete again.
Answers
-
Hello, @Collen Geter . Do you have "Duration" and "Predecessor" turned on? The parent rows' percentage is automatically calculated and is not editable. Did your project settings change and you no longer have start/end/ Complete%?.
Fernando Flores | M365 Enterprise Project Manager ✌️ 🍻
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.9K Get Help
- 474 Global Discussions
- 207 Use Cases
- 517 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 83 Community Job Board
- 521 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 309 Events
- 37 Webinars
- 7.3K Forum Archives