I manually changed the overall % Complete and now it won't auto calculate

Collen Geter
edited 11/22/21 in Smartsheet Basics

Because I hadn't filled in all my dates, I was asked for a number to represent where I thought we were. So I manually typed in over the % complete auto calculated field and now I can't get it to auto calculate the overall % complete again.

Answers

  • 404.IRL
    404.IRL ✭✭

    Hello, @Collen Geter . Do you have "Duration" and "Predecessor" turned on? The parent rows' percentage is automatically calculated and is not editable. Did your project settings change and you no longer have start/end/ Complete%?.

    Fernando Flores | M365 Enterprise Project Manager ✌️ 🍻