I manually changed the overall % Complete and now it won't auto calculate
Answers
-
Hello, @Collen Geter . Do you have "Duration" and "Predecessor" turned on? The parent rows' percentage is automatically calculated and is not editable. Did your project settings change and you no longer have start/end/ Complete%?.
Fernando Flores | M365 Enterprise Project Manager ✌️ 🍻
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 495 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives