I manually changed the overall % Complete and now it won't auto calculate
Answers
-
Hello, @Collen Geter . Do you have "Duration" and "Predecessor" turned on? The parent rows' percentage is automatically calculated and is not editable. Did your project settings change and you no longer have start/end/ Complete%?.
Fernando Flores | M365 Enterprise Project Manager ✌️ 🍻
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 430 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 146 Just for fun
- 63 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives