I manually changed the overall % Complete and now it won't auto calculate
Answers
-
Hello, @Collen Geter . Do you have "Duration" and "Predecessor" turned on? The parent rows' percentage is automatically calculated and is not editable. Did your project settings change and you no longer have start/end/ Complete%?.
Fernando Flores | M365 Enterprise Project Manager ✌️ 🍻