adjust date calculation formula to count calendar days instead od workdays
Hi -
I have 2 date fields:
- Travel End Date - entered manually
- REIM DUE DATE – needs to be “Travel End Date +30 calendar days”
The formula below works but it counts 30 workdays after Travel End Date.
How to I correct it to be 30 calendar days after Travel End Date?
=WORKDAY([Travel End date]@row, +30)
Thank you!
Answers
-
Hey @Tanya Brooks
Try
=[Travel End Date]@row + 30
This will add 30days to your travel date
Will this work for you?
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.7K Get Help
- 438 Global Discussions
- 152 Industry Talk
- 497 Announcements
- 5.3K Ideas & Feature Requests
- 85 Brandfolder
- 155 Just for fun
- 77 Community Job Board
- 509 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 307 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!