Linking Schedules to a Master Schedule
dale3ME
✭
Hi Team, My company has a master schedule that is at project phase level (Initiation, Planning, Execution, Monitor & Control and Project close. Is it possible to link in the project schedules (which have the same roll ups) to the master, so that % complete and dates that are rolled up in the project schedules update the master schedule?
All help appreciated
Dale
Answers
-
Hi @dale3ME
My undertanding is that you need to link the specific cells from the individual project schedules tot he master schedule and then use formulas in the masterschedule to add up the % complete and to roll up dates.
e.g.
Start Date: =MIN(CHILDREN())
End Date: =MAX(CHILDREN())
Hope this helps if you haven't found a solution yet.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.1K Get Help
- 351 Global Discussions
- 198 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 133 Brandfolder
- 127 Just for fun
- 127 Community Job Board
- 455 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 283 Events
- 36 Webinars
- 7.3K Forum Archives