Linking Schedules to a Master Schedule
dale3ME
✭
Hi Team, My company has a master schedule that is at project phase level (Initiation, Planning, Execution, Monitor & Control and Project close. Is it possible to link in the project schedules (which have the same roll ups) to the master, so that % complete and dates that are rolled up in the project schedules update the master schedule?
All help appreciated
Dale
Answers
-
Hi @dale3ME
My undertanding is that you need to link the specific cells from the individual project schedules tot he master schedule and then use formulas in the masterschedule to add up the % complete and to roll up dates.
e.g.
Start Date: =MIN(CHILDREN())
End Date: =MAX(CHILDREN())
Hope this helps if you haven't found a solution yet.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives