If you have dependencies enabled in the sheet (typical for a project plan), then the Finish date is calculated automatically based on the duration and other dependencies. So, since this is a calculated column, the sheet does not allow you to select a specific finish date as a cell link from another sheet.
If you need this ability you'll have to disable Dependencies (found under Project Settings). The downside is that you lose the automatic cascade of dates.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives