Hi Everyone,
I am trying to auto-populate dates based on a certain column, which would update/change/auto-pupulate future dates in other columns within my sheet
Example
IF I put in a date 01/03/2022 in BCA completion date
I would like RR Completion date to auto populate a due date of 01/05/2022 (due within 2 days
I would like the IT Solution date to auto populate a due date of 01/10/2022) due within 7 days from the BCA date)