How do I automatically set duration of one task to the same duration of another task?
This would be easy if I could set a formula like "=[Duration]1 but we can't. I've tried setting predecessors to 1SS, 1FF and that doesn't work either. Any ideas?
Best Answer
-
Hi @NavyPilot
There currently isn't a way to automatically have the duration match the same as a previous task; you could out in 1SS and then manually add in the same Duration number in order for the task to match the previous task. Please let the Product team know of your feedback on our project features by filling in this form, here!
Cheers,
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now
Answers
-
Hi @NavyPilot
There currently isn't a way to automatically have the duration match the same as a previous task; you could out in 1SS and then manually add in the same Duration number in order for the task to match the previous task. Please let the Product team know of your feedback on our project features by filling in this form, here!
Cheers,
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now -
Thanks @Genevieve P.
I've been pretty much doing that as a workaround but if you have many tasks with this condition, it just adds to the workload of maintaining.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.7K Get Help
- 376 Global Discussions
- 206 Industry Talk
- 437 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 129 Community Job Board
- 450 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 282 Events
- 32 Webinars
- 7.3K Forum Archives