How do I link two different Smart sheets schedules from different stakeholders
I have received two Schedules from a client and their designer and need to link them so that updates to each one is reflected on the second.
Is this possible?
Answers
-
Hi @P Broomberg
You can set up a one-way sync by using Cell Linking to bring data from one sheet into the other, see: Cell Links: Consolidate or Maintain Consistency of Data
Depending on the sheet set-up, you could also use cross-sheet formulas to bring in data from one sheet to the other as well. See this other Community post for an example: Need a Clear Example of Using INDEX and MATCH in lieu of HLOOKUP
An alternative would be to create a Report using the two sheets as the source. This would allow you to see the rows from each sheet in the same place. Any edits you make in a Report will then update the underlying sheet(s) as well. See: SmartStart: Reporting
Cheers,
Genevieve
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 143 Industry Talk
- 476 Announcements
- 5K Ideas & Feature Requests
- 84 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives