How can I have a dependency from one project sheet (Gantt/Grid) to another?
I have some projects that have related interdependencies. Is there a way to establish those relationships cross sheets?
Answers
-
Smartsheet does not currently have the functionality of linking dependencies across multiple sheets.
You could create a Report, bringing in key rows from each of your sheets and displaying it in Gantt view. Although the dates wouldn't be dependent, this would allow you to see them all in one view.
Please submit an Enhancement Request to the Product team when you have a moment!
Thanks,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
-
Hi SmartSheet Team
I am very keen to see inter-project dependencies in SmartSheet. The conversation above took place more than a year ago. How close are we to having it?
Thank you
-
This is very necessary. It´s a basic function that any proyect management plataform should have
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.3K Get Help
- 423 Global Discussions
- 221 Industry Talk
- 462 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 144 Just for fun
- 59 Community Job Board
- 463 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives