Update Request not allowing field to update

When sending out an Update Request, I'm being told that the recipients are not always able to update the Completion Date. It is the child of a parent, dependencies are enabled but there are none for these line items, and none of the columns/rows are locked. Thoughts? Thank you!
Best Answer
-
Hi @Emily T.
End Dates in Project sheets can't be updated through an Update Request when dependencies are enabled; this is due to background dependency calculations that act as a sort of "formula" in that cell, even if the row has no Predecessors. The row uses the Start Date and Duration to calculate the End Date.
That said, because of this calculation, you can adjust the End Date through an Update Request by having your users adjust the Duration of the Task, which will automatically adjust the End date in the sheet.
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Answers
-
Hi @Emily T.
End Dates in Project sheets can't be updated through an Update Request when dependencies are enabled; this is due to background dependency calculations that act as a sort of "formula" in that cell, even if the row has no Predecessors. The row uses the Start Date and Duration to calculate the End Date.
That said, because of this calculation, you can adjust the End Date through an Update Request by having your users adjust the Duration of the Task, which will automatically adjust the End date in the sheet.
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.9K Get Help
- 429 Global Discussions
- 146 Industry Talk
- 486 Announcements
- 5.2K Ideas & Feature Requests
- 86 Brandfolder
- 151 Just for fun
- 74 Community Job Board
- 498 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 305 Events
- 36 Webinars
- 7.3K Forum Archives