Project Planning: Percentage Complete from Dates
Hello I'm currently using Smartsheet for project planning.
I want a forecasted percentage complete on progress to date from baseline start to baseline finish.
Can anyone help please?
Thanks in advance! :)
Answers
-
@Andrée Starå one for you?
-
Can you provide an example of the dates at issue, and what a correct response is?
Because it sounds like you have a schedule baseline, but now we are off of the baseline, so, based on progress to date, you want to calculate an end date. It seems like we are missing a variable, which is how much progress you've made.
For example: If we forecast a task will take from Jan 1 to Jan 31, and I am sitting here on March 1, and you ask me when I will be done, it matters if I am 10% or 90% complete. Because if I am 50% complete, that means that it took me two months to get as far as I baselined I would get in two weeks, so things are taking 4x as long, so I should be done in two more months.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!