Dear Colleagues,
If anyone has come across this requirement, please share how to solve it. I have various categories in my project plan: Indoor Works, Outdoor Works, Testing and commissioning etc. Each category like that has a weight in a project. My colleagues who are already using the plan have manually filled in the % Complete column that rolls up completion from children to parents. Now I am asked to add weightage.
My natural thinking was that I should add a new column to add Weight, then add a new column to calculate % Complete * Weight. Not sure this is correct...
Thank you,
Nikita