Elapsed Date Thingamabob?
I am new to smartsheet and I have a lot to learn. Any help on this would be greatly appreciated. I am looking for a way to send a notification if the "approved" column is blank and 10 days have elapsed since the date in the "Date submitted" column. I have been working on this for at least 3 hours and I have not found anything that would help. TIA.
Answers
-
In your workflow, have the conditions set to "Approved" is blank and "Date Submitted" is not in the last 10 days.
-
In order to trigger the notification you can either run the automation daily at a set time and then set the conditions that "Approved" is blank and "Date Submitted" "is not in the last (days)" (enter 10)
-or-
You could create a column for "Approve by date" which equals Submit Date +10
Then you set your trigger on the "Approve by Date"
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.4K Get Help
- 394 Global Discussions
- 213 Industry Talk
- 449 Announcements
- 4.6K Ideas & Feature Requests
- 141 Brandfolder
- 132 Just for fun
- 131 Community Job Board
- 453 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 293 Events
- 35 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!