How can I set Project settings to look at both m-f 9-5 and 24/7
Hi Everyone
I have some parts of the business working Monday to Friday 9am-5pm and the manufacturing and quality sides of the business working 24/7. When setting a project plan, can I have the option to set some line items to calculate 24/7 vs M-F?
Thanks
Best Answer
-
You can use Elapsed Time in the duration of specific rows that are assigned to manufacturing and quality to ignore your working days.
For example, instead of 2d as your Duration, add an e in front: e2d
See: Work with Duration and Predecessors
Cheers,
Genevieve
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
Answers
-
You can use Elapsed Time in the duration of specific rows that are assigned to manufacturing and quality to ignore your working days.
For example, instead of 2d as your Duration, add an e in front: e2d
See: Work with Duration and Predecessors
Cheers,
Genevieve
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
-
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.1K Get Help
- 443 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 5K Ideas & Feature Requests
- 129 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 35 Webinars
- 7.3K Forum Archives