Push or pull a new cell value to other sheets
When a new project is created, a unique project ID is entered into a master project table/sheet. When that project ID is entered, I want to be able to automatically populate the project ID cell in two other sheets. Any direction and/or creative ideas are appreciated.
Regards,
Janet
Answers
-
Use your automation functions. Fairly standard and intuitive to set up.
-
Hi Daisyq,
Thanks for responding. For automations to work for me, I would need the functionality to change a cell in another sheet. You can only change a cell in the sheet where automation is created.
I could use the automation to copy a row to another sheet, but in this case the sheet columns vary significantly so that won't work for me.
-
I hope you're well and safe!
You could use cross-sheet formulas combined with either a VLOOKUP or INDEX/MATCH structure to connect the sheets, and when you update the source sheet, it will reflect on the destination sheet.
Another option would be to use so-called helper sheets. In short, copy the row to a helper sheet and then use my method described previously to get the values you need to another helper sheet, and then copy/move the row from that sheet to the main destination sheet.
Would any of those options work/help?
I hope that helps!
Be safe and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Andree, thanks for the input. Will test it out tomorrow and let you know.
-
Excellent!
Happy to help!
✅Remember! Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
I was able to get your suggested solution working today. Success!
I created two helper sheets, then to pull the project ID from the master table I used Index/Collect, then created the automations to move the rows to their corresponding production sheets. Once moved, cleared the cells through the automation.
Thanks again.
-
Excellent!
You're more than welcome!
✅Remember! Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.6K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 468 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 64 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!