Hey everyone, I'm new to smartsheet and I have a question regarding the project sheet.
Attached is a screenshot of my current data.
I have over 1200 data and they are already seperated by parent-child relationship.
Each task has a production score and the parent's score is calculated by summing up all of the children's score.
We have a weekly quota of 270000 production score a week (or 54000 daily), and I calculated how long it would take to complete the task by taking the row's production score and dividing it by the quota. This gives the results as shown in column11, which are the duration of each task daily.
I would like to know if there's a way to transfer the data from column11 to the duration column in a fast way because if I copy paste the entire column, there is the following error for parent rows: "Because this row has sub-tasks, this cell is a summary value and cannot be edited directly."
I have 200+ parent rows, so it will take a while to copy paste all the children rows manually into the duration column.