Difference between prerequisites and predecessors
When identifying prerequesites I have been "bundling" them as a predecessor column with various interpretations of "Start - Start", "Start - Finish", etc. Is this consistent with anyone's usage of prereq's to "translate" them into application with Gantt charts?
Thanks!
Answers
-
Hi @Dan73594
Depending on what you mean by "prerequisite", I would say yes, this sounds correct. The Predecessor column in Smartsheet allows you to link rows together with a specific relationship, such as Start-to-Start or Start-to-Finish, etc.
Here's a free webinar that goes through Smartsheet's Project Management sheet features that you may find helpful: SmartStart: Project Management
If this hasn't answered your question, it would be helpful to see a screen capture of your sheet with a little more context, but please block out sensitive data.
Cheers,
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.1K Get Help
- 430 Global Discussions
- 149 Industry Talk
- 490 Announcements
- 5.2K Ideas & Feature Requests
- 85 Brandfolder
- 154 Just for fun
- 74 Community Job Board
- 499 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 305 Events
- 36 Webinars
- 7.3K Forum Archives