Difference between prerequisites and predecessors
When identifying prerequesites I have been "bundling" them as a predecessor column with various interpretations of "Start - Start", "Start - Finish", etc. Is this consistent with anyone's usage of prereq's to "translate" them into application with Gantt charts?
Thanks!
Answers
-
Hi @Dan73594
Depending on what you mean by "prerequisite", I would say yes, this sounds correct. The Predecessor column in Smartsheet allows you to link rows together with a specific relationship, such as Start-to-Start or Start-to-Finish, etc.
Here's a free webinar that goes through Smartsheet's Project Management sheet features that you may find helpful: SmartStart: Project Management
If this hasn't answered your question, it would be helpful to see a screen capture of your sheet with a little more context, but please block out sensitive data.
Cheers,
Genevieve
Categories
- All Categories
- 14 Welcome to the Community
- 10.7K Get Help
- 63 Global Discussions
- 69 Industry Talk
- 385 Announcements
- 3.5K Ideas & Feature Requests
- 55 Brandfolder
- 125 Just for fun
- 50 Community Job Board
- 464 Show & Tell
- 40 Member Spotlight
- 44 Power Your Process
- 28 Sponsor X
- 234 Events
- 7.3K Forum Archives