Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Comparing Actual Duration to a Projected Duration with a +/- days
John Plecki
✭✭✭
Three columns used are Duration(dependent), Projected Duration(I initially copy all of the durations over when setting the project) and +/- days(calculates the difference between Duration and Projected Duration) The trick here is you need to strip the "d" from the value to allow computations.
=(VALUE(LEFT([Projected Duration]9, (LEN([Projected Duration]9) - 1)))) - (VALUE(LEFT(Duration9, (LEN(Duration9)))))
Comments
-
Cool! Did you also have a question?
-
No question. When contacted Smartsheet to see if this could be done they did not have answer. It was difficult because of the type of column and data within the cell. I wanted to share it with the community.
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 457 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives