Trying to Calculate % complet based off subtask completion. For example this should read as 33%.

Answers
-
Hi @Max Ahmed
I hope you're well and safe!
You can go into the Project Settings and activate the Dependencies feature and the % Complete column to get the % Complete roll up automatically in your sheet.
Did that work/help?
I hope that helps!
Be safe and have a fantastic weekend!
Best,
AndrΓ©e StarΓ₯ | Workflow Consultant / CEO @ WORK BOLD
β Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
AndrΓ©e StarΓ₯ | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E: andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
I don't have any dates on this. This is more of a checklist.
-
It will not let me do that rollup without dates