Hi,
I manage to get SS auto populate the due-date base on the start date. But is it possible to make the due date calculation is not including the weekend?
Example:
Start Date = 19 May 2017, Friday
Due Date is after 4 day of the start date, it should be 23 May 2017.
But becasue of the Sat & Sun, the due date should delay another 2 more days. So it should be 25 May 2017.
Now i am using this formula to get my due date : =DATEONLY([Date Confirm]5 + 4).
Please help. Thanks
Cheers
Quece