Hi There
Can one have a formula in a project plan that says if the "Activity " column is "Project Task" and the "% Complete" 10%, then Status is "In Progress". However, if the "Activity" is changed to "No Longer Applicable", or "Hold" - the "% Complete" remains unchanged, but the Status is then either "No Longer Applicable", or "Hold"?
In the Status column, there is a formula currently that says that if the % Complete= 0% then the Status is "Not Started", between 1% and 99% the Status = In Progress, and, if it is 100% then the Status = "Complete"
Thank you in advance
Dickson