Resource Management Integration with Workday for Vacation or Out of Office?

Hi all,
We currently use Resource Management and have our teams enter their vacation time to ensure we capture this for employees. We also currently have Workday which tracks vacations and absence.
Is there a way to integrate the two to pull the data from Workday?
Answers
-
Hi @summetg
There currently isn't a direct integration between Workday and Resource Management.
That said, you could potentially use Bridge if you have access to it, or the Resource Management API.
The "Create Assignment" Bridge module or / assignments API endpoint could be used to create leave assignments in Resource Management based on what's entered into Workday.
Cheers!
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
-
Thanks Genevieve this helps bring some insight.
Can that "Create Assignment" work as an "import" type function? I feel it is triggering the data to push to a system like Workday, not from?
-
Hi @summetg
The "Create Assignment" module in Bridge will create assignments in Resource Management when an event takes place elsewhere, for example in Workday. Is that what you were looking to do?
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.1K Get Help
- 430 Global Discussions
- 149 Industry Talk
- 490 Announcements
- 5.2K Ideas & Feature Requests
- 85 Brandfolder
- 154 Just for fun
- 74 Community Job Board
- 499 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 305 Events
- 36 Webinars
- 7.3K Forum Archives