Schedule Delta %
Hi, I encounter "#Unpaseable" error code on the "Schedule Delta (%) formula with a number of attempts. Tried following the example shown in the Smartsheet's PMO template example as well as make slight change to correct a possible typo on Syntax in the Smartsheet example. See attached doc that captures the screenshots of the 3 scenarios - A), B) and C) on the formula - B) is Smartsheet's example that may have possible typo on the Syntax "Duration@row".
Please share your observation what could have gone wrong.
regards,
PChuang
Answers
-
=IFERROR([Schedule Delta (Working Days)]@row / Duration@row, "")
Try this or share the file link.
Executive Manager PMO
00923455332351
-
Hi Naeem, I validated that have already set the Project Setting to what was suggested. Same error message "#Unpasaeable" persists. Are there any other possible bug somewhere that are unturned?
regards,
PChuang