Schedule Delta %
Hi, I encounter "#Unpaseable" error code on the "Schedule Delta (%) formula with a number of attempts. Tried following the example shown in the Smartsheet's PMO template example as well as make slight change to correct a possible typo on Syntax in the Smartsheet example. See attached doc that captures the screenshots of the 3 scenarios - A), B) and C) on the formula - B) is Smartsheet's example that may have possible typo on the Syntax "Duration@row".
Please share your observation what could have gone wrong.
regards,
PChuang
Answers
-
=IFERROR([Schedule Delta (Working Days)]@row / Duration@row, "")
Try this or share the file link.
Executive Manager PMO
00923455332351
-
Hi Naeem, I validated that have already set the Project Setting to what was suggested. Same error message "#Unpasaeable" persists. Are there any other possible bug somewhere that are unturned?
regards,
PChuang
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.9K Get Help
- 474 Global Discussions
- 208 Use Cases
- 517 Announcements
- 5.6K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 84 Community Job Board
- 521 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 309 Events
- 37 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!