Working days between two dates
Hi, I'm looking to use the networkdays forumla to calculate the working dates between my date column and the oldest column for each individual, I can't understand why the formula isn't working. I have set holidays to zero (and changed it to a number) and its still unparseable. Can anyone assist me with the correct forumla, please? Thank you
Answers
-
I hope you're well and safe!
Try something like this. (change the column names to match yours)
=NETWORKDAYS(Date@row, Oldest@row)
Did that work/help?
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.9K Get Help
- 379 Global Discussions
- 210 Industry Talk
- 441 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 300 Events
- 33 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!