FTE Calculations
Is there a way to track FTE resources using a percentage of their time for a specific task for a specific duration? When you assign a person to a task, Smartsheet seems always calculate a full resource rather than just a small percentage of that person's time. Because of that, our resources are always showing as over-allocated.
Best Answer
-
@CRW Have you added a column that is set as your Allocation % column?
If you do so, you should be able to specify a resource a certain allocation percentage, if Legacy Resource Management is enabled.
dm
Answers
-
@CRW Have you added a column that is set as your Allocation % column?
If you do so, you should be able to specify a resource a certain allocation percentage, if Legacy Resource Management is enabled.
dm
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.8K Get Help
- 474 Global Discussions
- 205 Use Cases
- 517 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 83 Community Job Board
- 521 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 309 Events
- 37 Webinars
- 7.3K Forum Archives