FTE Calculations
Is there a way to track FTE resources using a percentage of their time for a specific task for a specific duration? When you assign a person to a task, Smartsheet seems always calculate a full resource rather than just a small percentage of that person's time. Because of that, our resources are always showing as over-allocated.
Best Answer
-
@CRW Have you added a column that is set as your Allocation % column?
If you do so, you should be able to specify a resource a certain allocation percentage, if Legacy Resource Management is enabled.
dm
Answers
-
@CRW Have you added a column that is set as your Allocation % column?
If you do so, you should be able to specify a resource a certain allocation percentage, if Legacy Resource Management is enabled.
dm
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives