FTE Calculations

CRW
CRW ✭✭
edited 11/03/22 in Smartsheet Basics

Is there a way to track FTE resources using a percentage of their time for a specific task for a specific duration? When you assign a person to a task, Smartsheet seems always calculate a full resource rather than just a small percentage of that person's time. Because of that, our resources are always showing as over-allocated.

Best Answer

  • Dale Murphy
    Dale Murphy ✭✭✭✭✭✭
    Answer ✓

    @CRW Have you added a column that is set as your Allocation % column?

    If you do so, you should be able to specify a resource a certain allocation percentage, if Legacy Resource Management is enabled.

    dm

Answers

  • Dale Murphy
    Dale Murphy ✭✭✭✭✭✭
    Answer ✓

    @CRW Have you added a column that is set as your Allocation % column?

    If you do so, you should be able to specify a resource a certain allocation percentage, if Legacy Resource Management is enabled.

    dm