Dependency duration not displaying correctly. Start-to-Finish Issue.
Hi, I'm using dependencies to create timelines for projects where I type in a launch date and then all the previous rows fill in accordingly as a work back schedule. This feature used to work great, but I noticed last week that now if I have a duration of 1 day, my start and end dates span 2 days instead of 1. I set my project to 8 hour work days. When I type in the launch date, that shows the way I would expect, as the date from 8:00 AM - 4:59 PM on the same day, but then the next row referencing that date will start 5:00 PM 2 days previous and then end the following day at 4:59 PM. I know this because I put in a formula that gathers the dates and reflects the times back. Is there anything I can do so the previous row reflects a normal work day instead of the 2 days it shows in my pic below?
Answers
-
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives