Were dependencies recently modified or changed?
In the past, using the Finish to Finish function, the dates I would see are as below:
Line 1, 4w, 12/1/23 - 12/28/23
Line 2 (FF to Line 1), 1d, 12/28/23 - 12/28/23
Opening my project plans last week, I noticed that my dates for single day lines changed that anything FF with a duration 1d now span over TWO days.
Line 1, 4w, 12/1/23 - 12/28/23
Line 2 (FF to Line 1), 1d, 12/27/23 - 12/28/23
Is this a bug or is this the new way that dependencies work?
Best Answer
-
Hi @Amanda W
I checked in with the Support team this morning and they let me know that a fix has now been applied! You should now see the correct Start Dates for any rows with a FF or SF predecessor relationship.
Cheers,
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now
Answers
-
Hi @Amanda W
This is a reported issue that our team is investigating at the moment: predecessors with FF or SF links are showing the Start Date as one day earlier than it should be, based on the duration.
I don't have an ETA for when this will be resolved but we're actively working on a fix. In the meantime, if you set the duration to be slightly smaller than 1 (e.g. 0.9d) this will update the Start Date to the correct date.
Cheers,
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now -
Hi @Amanda W
I checked in with the Support team this morning and they let me know that a fix has now been applied! You should now see the correct Start Dates for any rows with a FF or SF predecessor relationship.
Cheers,
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 379 Global Discussions
- 213 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives