Set Start and End Date for Two Tasks
I'm trying to find a solution for populating a start and estimated completion date for two tasks simultaneously. For example, I use headings for Start Date, Est. Completion, and Completed. I have a task (Validate Scope) that should mirror the Start Date and Est. Completion of the Execution task (parent row). I tried using Start-to-Start and Start-to-Finish to accomplish this, but the Start and End date for the Validate Scope task remain the Start Date of the Execution parent row.
I've highlighted the cells in a screenshot of my sheet below:
Answers
-
Try setting two predecessors. The first would be Start/Start and the second would be Finfish/Finish.
Have you tried adjusting the duration so that it matches the Execution Duration?
-
Thanks, Paul.
I tried using the SS and FF dependencies but received a CIRCULAR error. I can adjust the duration manually, but you can't use a formula to = the time of another row (which would be ideal). The problem is I can adjust it now, but if the project gets pushed, the field will not update accordingly.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!