Hi
is it possible to send an automatic update request every 2 weeks without changing anything in the sheet to a contact in a column?
Many thanks
Peter
Hi Peter,
Yes, probably but I'll need some more details. Can you describe in more detail what you want to do?
I hope this helps you!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
It's simple
i have a todo list (screenshot). The task is delegated to someone -> contact in "delegiert an". Now smartsheet should send an update request ever 2 weeks to the contacts in "delegiert an". These guys have to update the "erledigt zu", add a comment, upload a file or request with no changes.
many thanks
Ok. That's what I thought.
Look here
Update request every two weeks
Andrée
not exactly. With this way i must make an update request in each row and i have to set the contact manually. I want smartsheet to do this without interaction and send the update request to the contact in the "delegiert an" column. This contact may change or there will be more than one contact.
Ok. As a workaround, you could set up an Alert & Action > Update Request that sends on a date in a specific cell, and for each row, on the sheet, you link that data from the top date (first date) that you update every two weeks.
Would that work?
correct ... but i have to update the date every two weeks manually or is there an other way ... My intention is to make no manual entry.
It could probably be automated thru Zapier or a similar service. You could also have an Update Request for the first date go to you, and you could update it that way. Almost what you want
If you don't require an update but just FYI to someone, you can can use (while inside the sheet: File-send as attachment:
Happy to help!
Have a fantastic week!
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…
Hello team! Hope you all are having a wonderful holiday season. I am trying to set up an automation that will send an email reminder one time when Next Update Date = 60 days, then another automation at 30d, etc. The key is I only want it to send the reminder one time when Next Update threshold is reached. Is this possible?…
Has anyone found a workaround for sharing Smartsheet reports externally without giving access to internal data? I currently have to download the data and transfer it onto excel to create a pivot table for our client and I want to find an easier way to do so. I also already create a dashboard for our client, but I wanted…