Hi,
I have the attached date Alert setup in my SmartSheet but cannot get the Alerts to "trigger" overnight. Can anyone assist in what I may be missing in the setup of the Alert?
Thanks, Paul.
Hi Paul,
im having the same trouble, I can get the update request to trigger but not the alert.
The idea is to have a simple managers alert if someone hasn’t completed a task by say 2 days after it finish or due date.
i have tried all sorts of ways to trigger the alert including manual on changes to sheet row but it won’t trigger.
I tried last night again to see if it would work with my admin rights but again it didn’t work.
?? I have put a ticket in to support.
Hi Paul and Jarrod,
Did you manage to get it working?
I hope this helps you!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Hey, I am using the below formula→ =INDEX({Source_Sheet_Entire_Table}, MATCH([Unique ID]@row , {Source_Sheet_ID_Column}, 0), 1) Although the answer should be "Project details" mentioned in Column 1, it says #No Match. What am I doing wrong?
I have inly one user in my trial account. When I am trying to upgrade to PRO plan it is defaulting for 2 users and not allowing me to upgrade the plan for only one user. Please help.
How can I delete old sheets I no longer use from my account?