Sign in to join the conversation:
Is there a way to visually/graphically see changes to an activity "before and after" on the Gantt or calendar view? I.E. if an activity is running longer than original input is there a way to show the original end point and the added time?
Not that I am aware of. Someone may have a solution but the limitations to the GANNT chart are just two dates.
Hi,
Maybe it could work to make a copy of the original plan and then show them both in a report.
Would that work?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Thank you for the comments-replies.
Happy to help!
Have a fantastic week!
Andrée
Have you thought about duplicating each task to show the actual vs. planned? You could have a row for planned and a row for actual? The Gannt chart would display the rows beside each other to visually see the differences. You can also adjust the colors of the ACTUAL gannt rows to differ from the other ones.
https://help.smartsheet.com/articles/516441-changing-the-color-of-gantt-calendar-bars
Rather than showing two different reports you would be able to show one Gannt that visually indicates where the project went off course and how it affected the rest of the project.
I'm receiving this message every time I try to open my sheets. I'm the only admin user. I have already performed proper troubleshooting, such as clearing the cache, logging in incognito, and logging out and back in, but the issue remains unresolved. It's been a few days, and I'm unable to track our projects and this…
I’ve created an automation that generates a document and forwards it to the individual specified in a cell. The line item also has several additional attachments associated with it. Is there a way to include those attachments with the generated document?
I have an automation set up that copies a row to another sheet each day. The automation itself works correctly, but the problem is that it copies the formulas rather than the values, which causes the formulas to break and return errors. How can I configure it to copy only the values instead of the formulas?