I have searched all the forums for the formula for the checkbox sum & none of them have worked for me. I need to total the sum of the checkboxes that are checked within a column.
I just needed to do this today.
enter '=COUNTIF', then select the entire column, and put '1' for checked.
=COUNTIF({On Track}, 1)
I don't know why, but its not working for me. I've tried this several times. I either get "unparseable" or Boolean Exp message.
It worked if it is not in the same column as the checkboxes! Is there a way to make it part of the same column so the totals are below the boxes?
If you make all of the lower rows Child rows (indent them) below the summary row, you could use...
=COUNTIFS(CHILDREN(), 1) + ""
@Paul Newcome this formula helped me tremendously! Now I am facing another challenging. I am now trying to SUM the COUNTIFS totals using a CHILDREN formula to show the overarching total. I have attached an image. When I just try a general =SUM(CHILDREN( formula, nothing populates in the cell and I still see the checkbox. When I tried totaling manually at one point, instead of a SUM I somehow merged the numbers into a string (i.e. instead of 5 + 4 + 1 creating 10, I got 541).
Any suggestions on how I can total up the 23 + 17 + 1 + 0 + 0 + 0 appropriately in the North America row?
@Jen V I am at a similar situation. Did you find a way to sum in the checkbox column?
Thanks in advance.
Hello, I'm working through the writing formulas optional activity and in the 'Nested IF function - Progress Column' task it directs you to put in the following formula '=IF([% Complete]@row = 0, “Empty”)'. However, when I put this formula into the spreadsheet, '04a_Marketing Request Tracker - Formulas', I get an…
I have an automation that has a condition where I am looking at the column "LEA Interco Supporting Site(s)" and trying to find columns that have the value "Fort Loramie" in them. This works well when "Fort Loramie" is the first item listed in the cell, but it doesn't work when "Fort Loramie" is the second or third value in…
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…