we have this issue in few smartsheet pages where assignment is not working properly. we assigned a person %10 (or any other percentages) to the work and no matter what we do, it shows %100.
Hi Leila,
Thanks for your post, I'm happy to help. Is it possible that the Allocation % column has not been set in the Project Settings? If this column has not been defined, Smartsheet will always default to 100%. To check this:
See the screenshot below for reference. More information about this can be found in the following links:
If you continue to experience issues, I recommend reaching out to our Technical Support team at https://help.smartsheet.com/contact
I hope this helps!
Isaac J
Smartsheet Support
Hello, I'm working through the writing formulas optional activity and in the 'Nested IF function - Progress Column' task it directs you to put in the following formula '=IF([% Complete]@row = 0, “Empty”)'. However, when I put this formula into the spreadsheet, '04a_Marketing Request Tracker - Formulas', I get an…
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…
I have had approval workflows and notifications built into a couple sheets for about a year now. In the past month, I am getting a lot of feedback saying people did not receive the email request for approval or notification email. It isn't all the time, just sometimes and there does not seem to be a pattern on which ones…