I am attempting to do the following.
If the "Completed" column has a check, in the checkbox, I would like the % Complete column to read 100%
Here is the formula I thought would work using task 4.of the project.
=IF(Completed4 = "Complete", "100%")
Found my error
The formula should have been
=IF(Completed4 = "true", "100%"
Here is another option.
=IF(Completed@row = 1, 1)
You will need to format your % complete column as a % but then it will load the actual % rather than text.
What if there are multiple status' that equal 100%? what would the formula be for that?
Hi all, I'm having some issues with an index-collect formula. I have (3) existing sheets that list a unique project name (text field), as well as a producer assigned to work that project. The producer column in all (3) sheets is set as a contact field. In a separate sheet, I'm trying to auto-populate the producer…
I am currently in business trial version, but i was told it is supposed to allow for full functionality, however when I click Ctr+F my search menu is only a search bar that allows me to only find the string, and it doesn't allow for replacing. Is it me or the F&R functionality rather limited?
I looking to find unique values, in order, and separate them into columns. The "Client Update Date" column will contain dates, not in order and some dates may be duplicated. In the "1st Date Feedback I'm getting the correct date of 12/12/25 with the formula: =MIN([Client Update Date]:[Client Update Date]) In the "2nd Date…