Sign in to join the conversation:
Greetings,
I have the start day and the duration. Is it possible to calculate the end date using these two entitites such that only working days are included (only monday through friday and not the weekends)?
Thank you
I would take a look at the WORKDAY function.
WORKDAY()
WORKDAY(date, num_days, [holidays])
Used in a Date column to return a date from a specified number of working days. Optionally excludes holidays outlined in a range.
Hmmm. You might also try turning on dependencies. It will set up a start time and a finish time column if you don't already have one and calculate the finish time for you. When you edit the start date or the duration, the end date will calculate for you automatically.
That might be a better way of doing it rather than using custom formulas.
Another added benefit of turning on dependencies is that you can also make the end of one task determine the beginning of the next one.
Thank you very much.
It worked!
Happy to help!
I would also suggest looking into dependencies as Mike suggested below. I don't use them for various reasons, so I never think about them as a solution.
Can this be done without using a function?
We want to implement single-sign-on at work and have received approval. However, our IT department wants all external partners to have/use Mayo credentials to log into Smartsheet. Not all of our external partners ever set foot on our campus and don't have our company credentials. I have a couple of questions. Has any other…
I can create a Chart in Dashboard from sheet well but from Report is not working now. I just try with simple Report (just contain 2 column Primary and Number) but cannot make the chart. Is there any changes recently right, because I haven't worked with Smartsheet dashboard for a long time and I remembered that I could do…
Cant find this anywhere