Resource mgmt - Allocating less (or more) than 8 hours a day for a resource

Options

All.

My team spends 15% of their time in other activities like meetings, career development, system support, etc. I would like to use Smartsheet resource mgmt functionality but only allocating approx 6 hours a day for my resources. How can I do that?

Thanks

Comments

  • Travis
    Travis Employee
    edited 07/09/15
    Options

    As of right now, it isn’t possible to set a working day to 6 hours, however after our release this Saturday (July 11th) you will have the ability to set how long your working days are. Stay tuned for more information on this functionality! 