I'm trying to total up the job value column based on weekly totals. Can I have the formula calculate the weeknumber or do I have to create a helper column?
Try replacing WEEKNUMBER(30) with WEEKNUMBER(@cell)=30.
=SUMIFS({SHIPPED JOBS Range 1}, {SHIPPED JOBS Range 5}, WEEKNUMBER(@CELL)=30)
I'm still getting #UNPARSEABLE
Try it with @cell in lower case:
=SUMIFS({SHIPPED JOBS Range 1}, {SHIPPED JOBS Range 5}, WEEKNUMBER(@cell)=30)
Now I'm getting a different error.. sorry, if feel high maintenance for something simple
Sorry, I forgot that Smartsheet gets confused by blanks in the date column. Try this:
=SUMIFS({SHIPPED JOBS Range 1}, {SHIPPED JOBS Range 5}, NOT(ISBLANK(@cell)), {SHIPPED JOBS Range 5}, WEEKNUMBER(@cell) = 30)
That did it! Thank you. Always learning:)
There are a few other solutions in addition to Brian's. Not to say that Brian's is wrong or that any of these are "better". Just showing a few other options that will all accomplish the same result in different ways while accounting for different things in different ways.
Brian's:
.
Using AND to incorporate both sets of criteria into the same range:
=SUMIFS({SHIPPED JOBS Range 1}, {SHIPPED JOBS Range 5}, AND(NOT(ISBLANK(@cell)), WEEKNUMBER(@cell) = 30))
Use ISDATE(@cell) instead of NOT(ISBLANK(@cell)). This will prevent an error if a text value happens to be in the Date column:
=SUMIFS({SHIPPED JOBS Range 1}, {SHIPPED JOBS Range 5}, AND(ISDATE(@cell), WEEKNUMBER(@cell) = 30))
Using an IFERROR to account for non-date values within the WEEKNUMBER function:
=SUMIFS({SHIPPED JOBS Range 1}, {SHIPPED JOBS Range 5}, IFERROR(WEEKNUMBER(@cell), 0) = 30)
Using a DATEONLY function (because dates within SUMIFS and COUNTIFS especially in cross sheet references can get VERY particular):
=SUMIFS({SHIPPED JOBS Range 1}, {SHIPPED JOBS Range 5}, WEEKNUMBER(DATEONLY(@cell)) = 30)
An additional note:
You may want to also consider exactly what data will be on the source sheet. If there can be an overlap in years, you may also want to account for that by using the YEAR function (or other various methods) to ensure you are pulling for ONLY [weeknumber 30 of 2019] and not [weeknumber 30 of 2019 + weeknumber 30 of 2018].
@PaulNewcome
Thank you for the additional help.
I'm trying to apply the same formula to another sheet (and used some of your recommendation) but I'm getting an error.. I'm trying to add the retainer values based on the Weeknumber again
Move one of the closing parenthesis from the end to after your @cell reference.
The way it is written in your screenshot is that you are looking for the weeknumber of DATEONLY(@cell) = 33 when really you are wanting the weeknumber of DATEONLY(@cell) to equal 33 (if that makes sense).
It should be
WEEKNUMBER(DATEONLY(@cell)) = 33)
It's still giving me incorrect arugument?
It could be your ranges. The range to sum should be first, then your date range. Also make sure the ranges are the same size.
The Range 4 is the Product Value Column and the Range 5 is the Retainer Date Column
I selected the entire column for both
Are there blanks or non-date values in your date column? Try wrapping your WEEKNUMBER function in an IFERROR to replace blanks and text values with a zero. The DATEONLY function SHOULD be taking care of that, but just to be sure.
IFERROR(WEEKNUMBER(DATEONLY(@cell)), 0) = 33
Yes! that did it. Thank you for your help
Happy to help!
I need a column formula that can add sequential, unique IDs to data like this coming in from a form: Task Type Task ID Manual M001 Automated Manual M002 Manual M003 Manual M004 Automated Manual M005 Task IDs that aren’t the manual type need sequential numbering within their type (i.e. A001, A002, etc). Here’s the kicker:…
I'm trying to display a sum of the column Total Funds Available when Status = Apps Open, and Value Score = 5. Here is the formula I have: =SUMIFS([Total Funds Available]:[Total Funds Available], Status:Status, ="Apps Open", [Value Score]:[Value Score], ="5") There are rows that meet these conditions and should display a…
Hi everyone. We have an upcoming project is very short, but very critical, and requires that we track not only the start and end dates, but also the start and end times. Currently our team has added two columns, start time & end time, and they would like to add a duration column that can track the planned duration in…