I would like the column "Done" to be checked automatically if the % Complete is changed to 100%. I am using the formula below which is not working:
=IF([% Complete]3 = "100%", 1)
Any suggestions?
If your % Complete column is formatted to be a percentage, you will need to replace "100%" with 1 (no quotes).
=IF([% Complete]@row= 1, 1)
thank you so much!!! it worked
Happy to help!
Smartsheet stores percentages as a fraction of 1, so
100% = 1
75% = 0.75
50% = 0.5
25% = 0.25
0% = 0
and everything in between.
Date Report Partner CBO Name 01/12/25 Children's org 05/15/25 Foodbank 08/30/25 Children's org 09/11/25 Chamber 11/25/25 Digital Bus 08/21/24 Digital Bus South 01/15/26 Children's org 01/12/24 Foodbank Sister 02/15/24 For the children org 07/01/26 Digital Bus #2 08/05/26 Family Center 12/01/26 Family Center I am trying to…
I am trying to get the passenger count per month per year, and I can't seem to get the formula correct. I need to add the number of passengers for each month per year. If anyone could assist me with this, I would greatly appreciate it. Thanks!
I need to edit a large sheet that has a lot of predecessors. I need to delete one row and move another. when I make the changes the predecessors for proceeding lines are not correctly displaying the dates correctly. Need help.