This is the senario:
Line 1:
Start date January 1st.
Duration 5 days
Line 2:
Start date January 15th.
Duration 5 days.
I want the two lines to be dependent so that line 2 can't start before line 1 is done.
However, Line 2 should not start before the 15th.
My problem is that if I create a dependency, the startdate of line 2 will automatically change to January 6th.