Dear All,
Can someone tell me what is the equivalent of MS Project constraints in Smartsheet. I have been reading of using Lag time but wanted to know if there is another way of doing it the same.
Many thanks,
Taru
Hello Taru,
Er du Norsk?
Smartsheet has dependencies built right in. You can use these to achieve what you're after.
If you locate the Predecessors column in your sheet, it will behave in a similar way to MS Project, with the ability to free type dependencies (e.g. 2FS + 2d, 24 etc.) or set them via the pop-up dialogue that appears when you click on the edit icon in each cell.
Hope this was what you are after.
That's a big big weak point of smartsheet not to be able to have the ability to constrain dates like in microsoft project and primavera.
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…