I've imported a project into a project sheet and now would like to level the resources that are overallocated so the schedule adjusts to show the actual schedule if I use these resources. Is there a way to do this?
Thanks in advance,
Sue
Hello,
Thanks for your post! Currently, there isn't a feature which will automatically level out or reschedule over-allocated resources in your project, but you can submit a Product Enhancement Request using the quick link to the right. You'll want to manually re-allocate your resources according to your needs. It may be helpful to insert two additional date columns for Planned vs Actual Start and Finish dates which can be switched in the Project Settings to give you different views of the sheet. I've linked some additional resources for this below:
I hope this helps!
Isaac JSmartsheet Support
This is disappointing. Unfortunately the lack of this feature disqualifies the software for my organization. Is this on any sort of roadmap?
Hi,
Have you looked at 10,000ft?
Smartsheet presented some more details about the 10,000ft capabilities at Engage.
More info: https://www.smartsheet.com/content-center/best-practices/engage-content/better-together-smartsheet-10000ft-story
https://www.10000ft.com/
More info: https://www.smartsheet.com/content-center/news/smartsheet-acquires-10000ft-enhance-resource-management-capabilities
Speaking more broadly, with the integration of 10,000ft, Smartsheet customers will benefit from the ability to plan and allocate resources across their projects, optimize resource allocation by function or skill set, track time against forecast, and gain real-time portfolio level visibility into the status of budgets and deliverables.
I hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
Hi, I currently have smartsheet and 10000ft but can not find the features that can level resources similar to MS project. Is there a leveling feature? We may have to switch back to MS Project because it is difficult as tasks move around to reallocate resources manually.
Also, is there a split-task feature because this also makes the process difficult when resources need to be shared among our tasks.
Has this been updated in recent years? I also need to level resources so a valid schedule is created. Is the only way to create a schedule to add predecessors in for each task?
Thanks,
James
Following on from James' comment, has this been updated? If not, I will have to give up on Smartsheet - without this feature it's too limited to justify its use.
All the best,
Enzo
Has anyone found a workaround for sharing Smartsheet reports externally without giving access to internal data? I currently have to download the data and transfer it onto excel to create a pivot table for our client and I want to find an easier way to do so. I also already create a dashboard for our client, but I wanted…
Hello team! Hope you all are having a wonderful holiday season. I am trying to set up an automation that will send an email reminder one time when Next Update Date = 60 days, then another automation at 30d, etc. The key is I only want it to send the reminder one time when Next Update threshold is reached. Is this possible?…
I have an automation setup to escalate to managers when a step goes beyond 2 days. I have that titled as Escalation for Purchasing, Escalation for Planning, etc. In my trial run, 3 out of 6 showed up as Reminder: New part number request log ( this is the name of the sheet) The only thing we could see was that the ones that…