Is there a workday.intl equivalent in SmartSheet?

Options

I am looking to pull in a google sheet used to manage project schedule that uses a 6 day work week to calculate schedules.

For example one cells formula is:

=IFERROR(if(E69="Mail Date", F69,if(G69="First", workday.intl(AN69,-4,11,Holidays_USPS), if(G69="Standard",workday.intl(AN69,-6,11,Holidays_USPS),"NA"))),"NA")

Is there a way to do similar calculation in SmartSheet?

I haven't found a way to define weekends like in the workday.intl.

Let me know.

Dave

Answers

  • Dale Murphy
    Dale Murphy ✭✭✭✭✭✭
    Options

    @Dave_S Have you activated the Gantt view in the sheet and set the working days in project settings?

    dm

  • Dave_S
    Options

    Thanks - no I have not. But unfortunately the working days is not consistent across all activities at the project level. The working days/holidays vary for the project task by owner group.

    The holidays I am able to vary by using references to a different range to define different.

    Dave