Is there a workday.intl equivalent in SmartSheet?
I am looking to pull in a google sheet used to manage project schedule that uses a 6 day work week to calculate schedules.
For example one cells formula is:
=IFERROR(if(E69="Mail Date", F69,if(G69="First", workday.intl(AN69,-4,11,Holidays_USPS), if(G69="Standard",workday.intl(AN69,-6,11,Holidays_USPS),"NA"))),"NA")
Is there a way to do similar calculation in SmartSheet?
I haven't found a way to define weekends like in the workday.intl.
Let me know.
Dave
Answers
-
@Dave_S Have you activated the Gantt view in the sheet and set the working days in project settings?
dm
-
Thanks - no I have not. But unfortunately the working days is not consistent across all activities at the project level. The working days/holidays vary for the project task by owner group.
The holidays I am able to vary by using references to a different range to define different.
Dave
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.3K Get Help
- 364 Global Discussions
- 199 Industry Talk
- 428 Announcements
- 4.4K Ideas & Feature Requests
- 136 Brandfolder
- 127 Just for fun
- 128 Community Job Board
- 445 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 283 Events
- 35 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!