Is there a workday.intl equivalent in SmartSheet?
I am looking to pull in a google sheet used to manage project schedule that uses a 6 day work week to calculate schedules.
For example one cells formula is:
=IFERROR(if(E69="Mail Date", F69,if(G69="First", workday.intl(AN69,-4,11,Holidays_USPS), if(G69="Standard",workday.intl(AN69,-6,11,Holidays_USPS),"NA"))),"NA")
Is there a way to do similar calculation in SmartSheet?
I haven't found a way to define weekends like in the workday.intl.
Let me know.
Dave
Answers
-
@Dave_S Have you activated the Gantt view in the sheet and set the working days in project settings?
dm
-
Thanks - no I have not. But unfortunately the working days is not consistent across all activities at the project level. The working days/holidays vary for the project task by owner group.
The holidays I am able to vary by using references to a different range to define different.
Dave
Help Article Resources
Categories
Check out the Formula Handbook template!