Hi All
My project plans have weekends turned off as the majority of our work is not completed on weekends.
However, occasionally we need to schedule work to be completed on the weekend. I read on this forum that you can use the elapsed time in your project by adding an "e" ahead of the duration. However, the only way I could manage to get this to work is by removing the Prefecessors which now causes a break in my critical path.
Does anyone know how to resolve it? Or a better way to do it?