Can I calculate % complete & % remaining from multiple project plans into master dashboard?
I need to calculate % complete and % remaining from multiple sheets into one master dashboard. I have 4 separate project plan sheets that have these percentages for the individual project sheet, but want to see the overall percentages complete/remaining for the 4 sheets as they are all part of one major project. I appreciate any assistance you can offer/suggest. Thanks.
Answers
-
Have you looked into putting the 4 sheets into a report and then using the grouping and/or summary features?
-
Hi Paul, I have created master reports for all the project plans, deliverables and risks. I'm not familiar with 'grouping' or summary features.
-
Hi @Tammy R
I hope you're well and safe!
More info.
Would that work/help?
I hope that helps!
Be safe, and have a fantastic weekend!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
You can create groups and summarize them right in a report. You could create a report that brings in all project plans, create a filter so that it only pulls in the row that contains the percentages you want, and then create a Summary to average those percentages.
Help Article Resources
Categories
Check out the Formula Handbook template!