Project Schedule Health from PMO Template
Answers
-
Hi @Marcia562,
Here is a revised version that will have activities that start in the next 10 days turn green:
=IF([% Complete]@row = 1, "Blue", IF([End Date]@row < TODAY(), "Red", IF(AND([Start Date]@row <= TODAY(), ABS(NETWORKDAYS(TODAY(), [Start Date]@row) + 1) / ABS(NETWORKDAYS([Start Date]@row, [End Date]@row)) > [% Complete]@row), "Yellow", IF(AND([Start Date]@row <= TODAY(), ABS(NETWORKDAYS(TODAY(), [Start Date]@row) + 1) / ABS(NETWORKDAYS([Start Date]@row, [End Date]@row)) <= [% Complete]@row), "Green", IF(AND([Start Date]@row > TODAY(), [Start Date]@row <= WORKDAY(TODAY(), 10)), "Green", "")))))
For best practices, please reference Advanced Formula Examples sheet in the Smartsheet Formula Examples Template (Smartsheet Formula Examples Template | Smartsheet).
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.7K Get Help
- 438 Global Discussions
- 152 Industry Talk
- 497 Announcements
- 5.3K Ideas & Feature Requests
- 85 Brandfolder
- 155 Just for fun
- 77 Community Job Board
- 509 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 307 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!