Baseline with indented rows
I have attached a screenshot for reference.
I have a task that is behind 161 days - Plan Organizational Change Management.
However, my rows are indented and it does not appear that my baselines are taking this into consideration. The baseline shows the task as 161 days behind, however, the overall for the Planning section is 0.
Is this intended?
Best Answer
-
Have you set predecessors in your project?
If not, the actual date change that does not affect the parent level date shows 0 variances at the parent level.
😀
Answers
-
Have you set predecessors in your project?
If not, the actual date change that does not affect the parent level date shows 0 variances at the parent level.
😀
-
I did not have predecessors set. Adding them resolved the issue.
Thanks so much for the help!
-
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives