Baseline with indented rows

I have attached a screenshot for reference.

I have a task that is behind 161 days - Plan Organizational Change Management.

However, my rows are indented and it does not appear that my baselines are taking this into consideration. The baseline shows the task as 161 days behind, however, the overall for the Planning section is 0.

Is this intended?