Hi,
I need some help with forumals which is not my strength, thanks in advance.
What I need is to set up KPI’s measure for my shipments.
There are 3 parties involved that need to complete their own step.
Once each step is completed by each party (regulatory, WHS and Logistics). it will record a date highlighted in the bellow screenshot.
What I am trying to do is that from the Date Requested if Regulatory took 2 days for approval it is a fail, below that is a pass.
Then on the WHS Completion if they take more than 3 days since the RA Approval Date it is a fail, below that pass.
And same for Logistics completion, if it takes more than 2 days from WHS Completion date is a fail below that is a passed.
Then I also would like to have a count of days, how many days does it take from the Date Requested to the Logistics Completion Date, and how many days are in between, is there a formula for that?
Thanks