Sign in to join the conversation:
We need to track the actual time spent on each task (daily and/or weekly) in addition to the percentage completed (gantt) . Any ideas how I can configure that?
Hi,
You'd have to add it manually.
Do you want to keep everything on one row per task? How many tasks and how many people?
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@getdone.se)
Hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
I need this too!
The cell value could be totaled or at least see/enter hrs spent on task(s) per day.
The GREATEST realization of this would be ability to add a number to a day cell in calendar portion of timeline.
Is this functionality inherently not possible per SSheet data-handling and display structure at code-level?
Thanks
@AMETICO , @K_Vento - were you able to acheive this? i am stuck there too…
@Andrée Starå below is the requirement - if your able to still support:
I have two columns in my sheet, one that is ACTUAL HOURS, and one that is WORKED HOURS.
Every time users enter worked hours, the workflow automation takes those hours into that user timesheet, and then clear the WORKED HOURS column so that user can re-enter other hours at any later point of time… at the end of the task (when we complete it), I want to know all the hours spent on this task, and that would be the comulative WORKED HOURS… I would like Actual Hours to be updated on the go whenever Worked Hours are added.
Ex:
Day 1-
Actual Hours = 0
Worked Hours = 5
*Missing* —> Actual Hours = 0+Worked Hours = 5
workflow clears Worked Hours —> Worked Hours = 0
workflow clears Worked Hours
Day 2-
Actual Hours = 5
Worked Hours = 3
*Missing* —> Actual Hours = 5+Worked Hours = 8
Hi, I hope you're well and safe! I've shared an example with you. Would that work/help? I hope that helps! Be safe, and have a fantastic day! Best,Andrée Starå | Workflow Consultant / CEO @ WORK BOLD ✅ Did my comment(s) help/answer your question or solve your problem? Please support the Community and me by marking it - Insightful 💡- Vote Up ⬆️ - Awesome ❤️ - or/and as the accepted answer. It will make it easier for others to find a solution or help to answer! I appreciate it, thanks!
I am attempted to export to excel. I have two different smartsheet documents to export. One of them exported to excel fine, but not the other. This happened a few weeks ago. I make sure all columns were the correct size & no cells were hidden. "We have found a problem with (file) Do you want us to try and recover as much…
Hello Smartsheet Community, I need some help with a report that I created and shared with a customer. The customer is not seeing any of the information that is pulling into the report. See screen shot below that the customer texted me. I do have the report filter only showing the customer their product pulling from our…
BLUF: When I create an Invoice, I need the cell-link to my live price data to be severed. I currently have a Price sheet for my products that is updated frequently. I use Control Center to create Projects, which includes an Invoice sheet. I have a dropdown on my invoice sheet to select a product, and then I use Index…