I have searched and attempted the WORKDAY formula without success.
I have a schedule that populates from this source and we have columns as shown.
to get the Est Finish Date i used formula =[Planned Install Date]@row + [Total Man Days]@row
This worked great except we dont work weekends and i would prefer if we can show the schedule report calendar that reads from this source not to include weekends. I looked at attempted to do workday and networkday formulas but seem to get an error. So there is a missing formula somewhere that i need help on.
My second part of this question is it possible to have within the formula to divide the man days in the column in 2/3/4 based on sizes.
IE: <10 man days divide by 2. 10-20 man days divide by 3 and 20+ man days divide by 4.
If thats not possible that is fine, i am mostly concerned with excluding weekends from the est finish date results on the calendar.
Here is a screenshot of the calendar view i am referencing wanting to remove the weekends.