Is there any way to have collaborators being able to open gantt charts at today's date instead of the earliest date?
Hi Doug,
There is a setting that you can change in the Project Settings. Please see attached link/screenshot.
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant / Get Done
Hi Andrée
thank you. Yes I have this turned on, but this setting is not available for collaborators and the setting only works for my log in.
Any other suggestions are very welcome.
thanks
Doug
Hi again Doug,
I just checked and yes that's correct. I'll come back to you if i discover someway to workaround it.
Please submit an Enhancement Request when you have a moment.
Need help: We are using an approval request automation where we would like to incorporate a SharePoint link rather than a file attachment to the request. We have a sheet column with the hyperlink, but it does not show up in the approval email or it shows up as a LONG URL. Needs to function both from desktop computer as…
I am the owner of a workspace that has multiple sheets and a dashboard. There are 3 Guests with Admin permissions for the whole workspace. They can edit the sheets, but not the dashboard. Is there a different type of permissions or some kind of limitations to dashboard editing for Guests?
I am looking at trying to build a multi-select option raffle form. Lets say a form user has 5 options or "tickets" they can put into a bucket of goods for a raffle. I would like for the user to put in any combination of entering tickets per good that they can with the five tickets they have. I will put in a picture of what…